EFFECTS OF INSTALLATION ON THE QUALITY OF DEEP FOUNDATIONS.


Introduction

All types of deep foundations can be damaged by improper methods of construction. As noted by Lacy and Moskowitz (1993), the engineer has several responsibilities prior to and during construction. Specifications for construction must be prepared that give the methods to be used to achieve foundations of good quality. Also, it is critical for qualified inspectors to be present during construction to ensure compliance with the specifications. The selection of a qualified contractor with experience with the proposed system and with proper equipment is vital, and the owners of the project should allow procedures that ensure a qualified contractor, such as prequalification of bidders. Preconstruction meetings with the successful contractor are almost always useful.

Driven Piles

Piles are sometimes damaged by overdriving. The waveequation method is useful to select an appropriate pile hammer for the pile to be driven. Attention to detail is important concerning such things as the driving equipment, the quality of the pile being driven, and the arrangements of the components of the system. Even with the use of an appropriate hammer and appurtenances, tough piles such as H-piles can be damaged at their ends by overdriving.

Damage of steel piles in unusual ways can involve great expense and loss of time. Open-ended steel pipes were being driven to support an offshore platform when the lower ends were distorted by being banged against the template structure. The distortion caused the lower portion of the piles to buckle inward during driving due to lateral forces from the soil. The collapse prevented drilling through the piles to allow the installation of grouted inserts.

Many engineers worked for several months to design a remedial foundation. Damage to precast concrete piles during driving can be vexing and expensive. The authors are aware of a bridge along the coast of Texas where many of the precast piles had been damaged due to overdriving, causing tensile cracks at intervals along the piles. Salt water entered the cracks, corroded the reinforcing steel, and destroyed the integrity of the piles. The contractor worked beneath the deck of the bridge to install a special system of drilled piles.

Selection and proper replacement of cushioning material when driving concrete piles is important (Womack et al., 2003). The authors were asked to review the installation of concrete piles where plywood was used as cushioning material. Driving continued until the plywood actually collapsed and burned due to continued use. The concrete piles exhibited a number of cracks in the portions above the ground.

Drilled Shafts

Drilled shafts or bored piles are becoming increasingly popular for several reasons. The noise of installation is less than that of driven piles, drilling can penetrate soft rock to provide resistance in side resistance and end bearing, and diameters and penetrations are almost without limit.

Drilled shafts are discussed in Chapter 11, and construction methods are described in detail in Chapter 5.
As noted earlier, preparation of detailed specifications for construction of drilled shafts is essential, and a qualified, knowledgeable engineer must provide inspection. Preconstruction meetings are highly desirable to ensure that the specified details of construction are consistent with the contractor’s ability to construct the project.

CFA Piles

As noted earlier, CFA piles have been used for many years and are competitive with respect to the cost per ton of load to be supported when the subsurface conditions are suitable. The CFA pile is constructed by rotating a hollow-stem CFA into the soil to the depth selected in the design. Cement grout is then injected through the hollow stem as the auger is withdrawn.

Two errors in construction with CFA piles must be avoided: (1) the mining of soil when an obstruction is encountered and the auger continues to be rotated and (2) abrupt withdrawal of the auger, allowing the supporting soil to collapse, causing a neck in the pile. To assist in preventing these two construction problems, a data-acquisition system can be utilized to record rotations, grout pressure, and grout volume, all as a function of penetration of the auger. Alternatively, the inspector can obtain such data on each pile as construction progresses.

Other Types of Piles

Many other types of piles for deep foundations are described in Chapter 5. The engineer must understand the function of such piles and the details of the construction methods. Preparation of appropriate specifications for construction and inspection of construction are essential. Field load tests of full-sized piles often must be recommended if such experimental data are unavailable from sites where the subsurface conditions are similar.

0 comments:

Post a Comment